In April 2018 the Council took on responsibility for managing weeds across the District on behalf of Hertfordshire County Council.
This includes directly managing the weed spraying programme, which has previously been undertaken by Hertfordshire County Council.
This arrangement will improve management of weeds across the District and the treatment frequency has be increased to three per year where necessary.
St Albans City & District Council will not be treating weeds from designated high-speed routes (such as the A414).
In 2019 weed treatment will be carried out in the following areas during April, July and September/October.
Please click on the button below to see if your street is covered.
Click on the button below to open the District Map Services. The pink lines along the middle of the roads indicate that we will be treating the weeds of those roads. If there is no pink line it means the roads will not be treated by the Council.
2019
Area | Description | Scheduled Start Date | Status & Date Completed |
Area 1 | City Centre and Central Areas | 22nd July | Complete |
Area 2 | New Green, Batchwood and Inner Marshalswick | 22nd July | Complete |
Area 3 | Jersey Farm, Outer Marshalswick and Oaklands to Fleetville | 29th July | Complete |
Area 4 | Oaklands to Fleetville, Highfield and Camp | 29th July | Complete |
Area 5 | King Harry, Cottonmill and Whitecroft | 22nd July | Complete |
Area 6 | Harpenden, West | 5th August | Complete |
Area 7 | Harpenden North | 5th August | Complete |
Area 8 | Harpenden East and South | 5th August | Complete |
Area 9 | Batford and Wheathampsted | 5th August | Complete |
Area 10 | London Colney and Colney Heath, Smallford | 12th August | In progress |
Area 11 | Chiswell Green and Park Street | 12th August |
|
Area 12 | Redbourn | 5th August | Complete |
These dates are subject to change as a result of wet and windy weather conditions